To conduct a safety diagnosis of the rail system design in 18 fields such as technical standards of rail facilities from the perspective of users and 396 diagnosis items and to eliminate the risk factors identified from the diagnosis before starting the construction of rail facilities to ensure the safety and convenience of users
Subject
Rail track/facilities construction with total distance of more than 1 km including 1 or more station(s)
Major tasks
- Diagnosis of turnkey projects commissioned to a private constructor encompassing all processes such as design and construction
- Diagnosis on general projects, separating design and construction
- Performance management and operation of information system on the safety diagnosis of the entire rail system
- Establishing and implementing training on rail system safety diagnosis
Diagnosis procedure
-
Selecting and contracting the party to conduct diagnosisNext
- Requesting outsourcing to the traffic safety diagnosis organization
Ordering organization
-
Providing base materials and dataNext
- Providing design documents, project report, etc,
Ordering organization Next TS or other safety diagnosis organization
-
Holding the kick-off meetingNext
- Discussing the diagnosis plan
Ordering organization, Designer, TS or other safety diagnosis organization
-
Reviewing the design documentsNext
- Based on checklist, diagram, and related materials
※ Conduct on-site inspection as needed
TS or other safety diagnosis organization
- Based on checklist, diagram, and related materials
-
Prepare the diagnosis reportNext
- Identify rail safety defects or recommended improvements
TS or other safety diagnosis organization
-
Hold the closing meetingNext
- Discussion on diagnosis results
Ordering organization, Designer, TS or other safety diagnosis organization
-
Decision on diagnosis resultsNext
- Change of design as needed
- No change of design unless needed
Ordering organization
-
ClosureNext
-
Submit the diagnosis results
Ordering organization Traffic administration organization